Production Line in a New Building
General Contractors
Initial Situation
The customer was often obliged to turn down orders since he had neither the machines nor the space to manufacture certain sizes. Orders that were taken could only be processed by employing additional resources and taking extra time.The decision to erect a new building complete with new machines was taken in consultation with the customer. The incorporation of both upstream and downstream production stages had to be taken into account. Apart from reducing throughput times, the objective was to minimize processing times and handling distances despite the addition of a new factory hall.Key Parameters
Industry: | Industrial enterprise |
Dimensions: | Dimensions of workpieces to be processed: |
Processing steps: | Transport, alignment, grinding, edging |
Project throughput time: | 24 months |
Project staff: | > 100 |
Newly developed machines: | 10 |
Solution
Erection of a turn key plant
- Planning of building in consultation with architects
- Design of special precision foundations
- Handling of official applications and approvals
- Tendering process for construction stages Evaluation of tenders
- Monitoring of construction progress
Implementation of machinery:
- Technical engineering: design of special precision foundations
- Basic engineering: design of machines
- Detail engineering: preparation of workshop drawings, production of parts lists
- Obtaining tenders from suppliers
- Evaluation of tenders Monitoring of production progress
- Preparation of documentation and CE markings
- Carrying out installation work
- Commissioning
- Training customer's staff to operate the new equipment